A CCTV installation is a power project as much as a network project. The switch sits in the middle of both, and most callbacks in the first year trace back to a decision made on the switch specification.
Start with the camera count, then add spare ports. Two spare ports on a 16-camera job is not generosity, it is planning: one for a camera added during commissioning, one for a temporary unit when a camera is replaced. Round up to the next standard chassis size rather than buying an exact-fit switch.
Then read the datasheets properly. A fixed 4 MP dome is often quoted at 5 to 7 W, but that is typical draw at room temperature with IR off. A varifocal bullet with IR on can double that. A PTZ with a heater can reach 40 W. Use the worst case, and remember that the switch has to survive the moment when every IR illuminator and heater switches on together.
Convert device watts into a switch budget. PoE conversion is roughly 85 percent efficient, so 200 W of cameras means about 235 W drawn from the switch supply. Add 20 to 30 percent for inrush current, cold-weather draw and the switch itself. A 16-port PoE+ switch with a 250 W budget is a sensible target for sixteen 10 W cameras; a 16-port unit sold with 120 W is not, even though the port count looks right.
Decide the uplink before you buy. Sixteen 4 MP cameras at H.265 and 15 fps produce roughly 40 to 60 Mbps, which one gigabit uplink carries easily. If the recorder sits on the same switch, camera-to-NVR traffic never crosses the uplink at all. Where cameras are spread across buildings, use SFP ports and fibre between cabinets instead of long copper runs.
Check four features that matter in the field and rarely appear in marketing pages. First, per-port PoE scheduling or watchdog: the ability to power-cycle a single port remotely turns a site visit into a two-minute fix. Second, VLAN support: cameras should live on their own VLAN, separate from office traffic and from the recorder management interface. Third, surge protection on the PoE ports, especially for cameras mounted on poles or building exteriors. Fourth, a fan or fanless design that matches the cabinet: fanless units are quieter and more reliable in dusty rooms, but need free air and a lower ambient temperature.
Installation practice decides the rest. Keep every run under 100 metres of actual cable route, not the straight-line distance. Terminate to T568B consistently and test every link before the cameras are mounted. Label each port to its camera location at installation time. Leave service loops at both ends, and do not bundle twenty PoE cables into one tight conduit in a hot ceiling without thinking about heat.
Finally, document what you installed: switch model, firmware version, port-to-camera map, power budget used and spare capacity. The next person on site, including future you, will need it.
If you are planning a CCTV project, send the camera models, quantities and maximum cable runs. We will return a port plan, a power budget calculation and a switch configuration that matches the site.